| ID |
Task Name |
Duration |
Start |
Finish |
Resource Names |
% Complete |
| 1 |
Project Quotes |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty Dog Properties Project Manager |
100% |
| 2 |
Get Quotes for Well |
2 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
Salty Dog Properties Project Manager |
100% |
| 3 |
Get Quotes for excavation footers and drain field |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty Dog Properties Project Manager |
100% |
| 4 |
Get Quotes for Masonry work |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty Dog Properties Project Manager |
100% |
| 5 |
Place Orders |
90 days |
Wed 2/12/03 |
Mon 5/12/03 |
Salty Dog Properties order processing |
100% |
| 6 |
Place work order with excavator |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
Salty Dog Properties order processing |
100% |
| 7 |
Place order with Block/Brick supplier |
2 hrs |
Wed 2/12/03 |
Wed 2/12/03 |
|
100% |
| 8 |
Place work order with Mason |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
Salty Dog Properties order processing |
100% |
| 9 |
Order Well |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
Salty Dog Properties order processing |
100% |
| 10 |
Order Gravel, etc for driveway |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
|
100% |
| 11 |
Order House from manufacturer |
90 days |
Wed 2/12/03 |
Mon 5/12/03 |
Salty Dog Properties order processing |
100% |
| 12 |
Lot Preparation |
45 days |
Mon 2/10/03 |
Wed 3/26/03 |
Excavation Crew |
100% |
| 13 |
Lot Clearing |
5 days |
Mon 2/10/03 |
Fri 2/14/03 |
Excavation Crew |
100% |
| 14 |
Construction Drive Installation |
2 days |
Mon 2/10/03 |
Tue 2/11/03 |
Excavation Crew |
100% |
| 15 |
Excavate for Footers |
1 day |
Tue 2/18/03 |
Tue 2/18/03 |
Excavation Crew |
100% |
| 16 |
Pour Footers |
1 day |
Wed 2/19/03 |
Wed 2/19/03 |
Excavation Crew |
100% |
| 17 |
Prepare Crawl Space/Basement |
1 day |
Fri 2/21/03 |
Fri 2/21/03 |
Excavation Crew |
100% |
| 18 |
Foundation Block Work |
5 days |
Mon 2/24/03 |
Fri 2/28/03 |
Masonry Crew |
100% |
| 19 |
Well Installation |
2 days |
Tue 3/25/03 |
Wed 3/26/03 |
Well Subcontractor |
100% |
| 20 |
Get Commitments |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty Dog Properties Project Manager |
100% |
| 21 |
Get Delivery date from Manufacturer |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty Dog Properties Project Manager |
100% |
| 22 |
Get Commitment from erector |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty Dog Properties Project Manager |
100% |
| 23 |
Get Commitment from Crane Company |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty Dog Properties Project Manager |
100% |
| 24 |
Subcontractor Notification |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty Dog Properties Project Manager |
100% |
| 25 |
Notify Erector |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty Dog Properties Project Manager |
100% |
| 26 |
Notify Crane Company |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty Dog Properties Project Manager |
100% |
| 27 |
Notify Plumbing Contractor |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty Dog Properties Project Manager |
100% |
| 28 |
Notify HVAC Contractor |
1 hr |
Tue 2/11/03 |
Tue 2/11/03 |
|
100% |
| 29 |
Notify Electrical Contractor |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty Dog Properties Project Manager |
100% |
| 30 |
Weather Status Check |
1 hr |
Sun 5/11/03 |
Sun 5/11/03 |
Salty Dog Properties Project Manager |
100% |
| 31 |
Make Go or No Go determination |
0.25 hrs |
Sun 5/11/03 |
Sun 5/11/03 |
Salty Dog Properties Project Manager |
100% |
| 32 |
House Completion |
35.75 days |
Mon 5/12/03 |
Mon 6/16/03 |
Salty Dog Properties Project Manager |
100% |
| 33 |
Receive house |
8 hrs |
Mon 5/12/03 |
Mon 5/12/03 |
Erector Crew |
100% |
| 34 |
Set and weather House |
1 day |
Tue 5/13/03 |
Tue 5/13/03 |
Erector Crew |
100% |
| 35 |
Electrical Hookups and Finished |
2 days |
Wed 5/14/03 |
Thu 5/15/03 |
Electrical Crew |
100% |
| 36 |
HVAC installation |
3 days |
Wed 5/14/03 |
Fri 5/16/03 |
HVAC Crew |
100% |
| 37 |
Siding Installation |
5 days |
Mon 5/19/03 |
Fri 5/23/03 |
Carpentry Crew |
100% |
| 38 |
Interior Finish |
9 days |
Sat 5/24/03 |
Sun 6/1/03 |
Carpentry Crew |
100% |
| 39 |
Flooring Installation |
3 days |
Mon 6/2/03 |
Wed 6/4/03 |
Flooring Subcontractor |
100% |
| 40 |
Plumbing Hookups (exterior) |
4 days |
Wed 5/14/03 |
Sat 5/17/03 |
Plumbing Crew |
100% |
| 41 |
Plumbing fixture installation |
2 days |
Mon 5/19/03 |
Tue 5/20/03 |
Plumbing Crew |
100% |
| 42 |
Electrical inspection |
2 hrs |
Tue 6/10/03 |
Tue 6/10/03 |
Local Building Authority |
100% |
| 43 |
Plumbing inspection |
2 hrs |
Tue 6/10/03 |
Tue 6/10/03 |
Local Building Authority |
100% |
| 44 |
HVAC inspection |
2 hrs |
Tue 6/10/03 |
Tue 6/10/03 |
Local Building Authority |
100% |
| 45 |
Final Grading |
1 day |
Fri 6/6/03 |
Fri 6/6/03 |
Excavation Crew |
100% |
| 46 |
Landscaping |
3 days |
Wed 6/11/03 |
Sat 6/14/03 |
Lanscaping contractor |
100% |
| 47 |
Final Cleanup |
1 day |
Sat 6/14/03 |
Sun 6/15/03 |
Carpentry Crew |
100% |
| 48 |
Receive U and O |
1 day |
Sun 6/15/03 |
Mon 6/16/03 |
Salty Dog Properties Project Manager |
100% |