Statement of Work for
a Finished Home

Pricing by Model

 




Project Start:
Project Finish:
Mon 2/10/03
Mon 6/16/03

Tasks

ID Task Name Duration Start Finish Resource Names % Complete
1 Project Quotes 1 day Mon 2/10/03 Mon 2/10/03 Salty Dog Properties Project Manager 100%
2 Get Quotes for Well 2 hrs Mon 2/10/03 Mon 2/10/03 Salty Dog Properties Project Manager 100%
3 Get Quotes for excavation footers and drain field 1 day Mon 2/10/03 Mon 2/10/03 Salty Dog Properties Project Manager 100%
4 Get Quotes for Masonry work 1 day Mon 2/10/03 Mon 2/10/03 Salty Dog Properties Project Manager 100%
5 Place Orders 90 days Wed 2/12/03 Mon 5/12/03 Salty Dog Properties order processing 100%
6 Place work order with excavator 1 hr Wed 2/12/03 Wed 2/12/03 Salty Dog Properties order processing 100%
7 Place order with Block/Brick supplier 2 hrs Wed 2/12/03 Wed 2/12/03   100%
8 Place work order with Mason 1 hr Wed 2/12/03 Wed 2/12/03 Salty Dog Properties order processing 100%
9 Order Well 1 hr Wed 2/12/03 Wed 2/12/03 Salty Dog Properties order processing 100%
10 Order Gravel, etc for driveway 1 hr Wed 2/12/03 Wed 2/12/03   100%
11 Order House from manufacturer 90 days Wed 2/12/03 Mon 5/12/03 Salty Dog Properties order processing 100%
12 Lot Preparation 45 days Mon 2/10/03 Wed 3/26/03 Excavation Crew 100%
13 Lot Clearing 5 days Mon 2/10/03 Fri 2/14/03 Excavation Crew 100%
14 Construction Drive Installation 2 days Mon 2/10/03 Tue 2/11/03 Excavation Crew 100%
15 Excavate for Footers 1 day Tue 2/18/03 Tue 2/18/03 Excavation Crew 100%
16 Pour Footers 1 day Wed 2/19/03 Wed 2/19/03 Excavation Crew 100%
17 Prepare Crawl Space/Basement 1 day Fri 2/21/03 Fri 2/21/03 Excavation Crew 100%
18 Foundation Block Work 5 days Mon 2/24/03 Fri 2/28/03 Masonry Crew 100%
19 Well Installation 2 days Tue 3/25/03 Wed 3/26/03 Well Subcontractor 100%
20 Get Commitments 1 day Mon 2/10/03 Mon 2/10/03 Salty Dog Properties Project Manager 100%
21 Get Delivery date from Manufacturer 1 day Mon 2/10/03 Mon 2/10/03 Salty Dog Properties Project Manager 100%
22 Get Commitment from erector 1 day Mon 2/10/03 Mon 2/10/03 Salty Dog Properties Project Manager 100%
23 Get Commitment from Crane Company 1 day Mon 2/10/03 Mon 2/10/03 Salty Dog Properties Project Manager 100%
24 Subcontractor Notification 1 day Tue 2/11/03 Tue 2/11/03 Salty Dog Properties Project Manager 100%
25 Notify Erector 1 day Tue 2/11/03 Tue 2/11/03 Salty Dog Properties Project Manager 100%
26 Notify Crane Company 1 day Tue 2/11/03 Tue 2/11/03 Salty Dog Properties Project Manager 100%
27 Notify Plumbing Contractor 1 day Tue 2/11/03 Tue 2/11/03 Salty Dog Properties Project Manager 100%
28 Notify HVAC Contractor 1 hr Tue 2/11/03 Tue 2/11/03   100%
29 Notify Electrical Contractor 1 day Tue 2/11/03 Tue 2/11/03 Salty Dog Properties Project Manager 100%
30 Weather Status Check 1 hr Sun 5/11/03 Sun 5/11/03 Salty Dog Properties Project Manager 100%
31 Make Go or No Go determination 0.25 hrs Sun 5/11/03 Sun 5/11/03 Salty Dog Properties Project Manager 100%
32 House Completion 35.75 days Mon 5/12/03 Mon 6/16/03 Salty Dog Properties Project Manager 100%
33 Receive house 8 hrs Mon 5/12/03 Mon 5/12/03 Erector Crew 100%
34 Set and weather House 1 day Tue 5/13/03 Tue 5/13/03 Erector Crew 100%
35 Electrical Hookups and Finished 2 days Wed 5/14/03 Thu 5/15/03 Electrical Crew 100%
36 HVAC installation 3 days Wed 5/14/03 Fri 5/16/03 HVAC Crew 100%
37 Siding Installation 5 days Mon 5/19/03 Fri 5/23/03 Carpentry Crew 100%
38 Interior Finish 9 days Sat 5/24/03 Sun 6/1/03 Carpentry Crew 100%
39 Flooring Installation 3 days Mon 6/2/03 Wed 6/4/03 Flooring Subcontractor 100%
40 Plumbing Hookups (exterior) 4 days Wed 5/14/03 Sat 5/17/03 Plumbing Crew 100%
41 Plumbing fixture installation 2 days Mon 5/19/03 Tue 5/20/03 Plumbing Crew 100%
42 Electrical inspection 2 hrs Tue 6/10/03 Tue 6/10/03 Local Building Authority 100%
43 Plumbing inspection 2 hrs Tue 6/10/03 Tue 6/10/03 Local Building Authority 100%
44 HVAC inspection 2 hrs Tue 6/10/03 Tue 6/10/03 Local Building Authority 100%
45 Final Grading 1 day Fri 6/6/03 Fri 6/6/03 Excavation Crew 100%
46 Landscaping 3 days Wed 6/11/03 Sat 6/14/03 Lanscaping contractor 100%
47 Final Cleanup 1 day Sat 6/14/03 Sun 6/15/03 Carpentry Crew 100%
48 Receive U and O 1 day Sun 6/15/03 Mon 6/16/03 Salty Dog Properties Project Manager 100%

 


Resources

ID Name Group Max Units Peak Units
1 Salty Dog Properties Project Manager   100% 0%
2 Salty Dog Properties order processing   100% 0%
3 Excavation Crew   100% 0%
4 Masonry Crew   100% 0%
5 Erector Crew   100% 0%
6 Electrical Crew   100% 0%
7 HVAC Crew   100% 0%
8 Carpentry Crew   100% 0%
9 Flooring Subcontractor   100% 0%
10 Plumbing Crew   100% 0%
11 Local Building Authority   100% 0%
12 Lanscaping contractor   100% 0%
13 Well Subcontractor   100% 0%


Assignments

Task ID Task Name Resource Name Work Start Finish % Work Complete
1 Project Quotes Salty Dog Properties Project Manager 8 hrs Mon 2/10/03 Mon 2/10/03 100%
2 Get Quotes for Well Salty Dog Properties Project Manager 2 hrs Mon 2/10/03 Mon 2/10/03 100%
3 Get Quotes for excavation footers and drain field Salty Dog Properties Project Manager 8 hrs Mon 2/10/03 Mon 2/10/03 100%
4 Get Quotes for Masonry work Salty Dog Properties Project Manager 8 hrs Mon 2/10/03 Mon 2/10/03 100%
5 Place Orders Salty Dog Properties order processing 720 hrs Wed 2/12/03 Mon 5/12/03 100%
6 Place work order with excavator Salty Dog Properties order processing 1 hr Wed 2/12/03 Wed 2/12/03 100%
8 Place work order with Mason Salty Dog Properties order processing 1 hr Wed 2/12/03 Wed 2/12/03 100%
9 Order Well Salty Dog Properties order processing 1 hr Wed 2/12/03 Wed 2/12/03 100%
11 Order House from manufacturer Salty Dog Properties order processing 720 hrs Wed 2/12/03 Mon 5/12/03 100%
12 Lot Preparation Excavation Crew 240 hrs Tue 2/25/03 Wed 3/26/03 100%
13 Lot Clearing Excavation Crew 40 hrs Mon 2/10/03 Fri 2/14/03 100%
14 Construction Drive Installation Excavation Crew 16 hrs Mon 2/10/03 Tue 2/11/03 100%
15 Excavate for Footers Excavation Crew 8 hrs Tue 2/18/03 Tue 2/18/03 100%
16 Poor Footers Excavation Crew 8 hrs Wed 2/19/03 Wed 2/19/03 100%
17 Prepare Crawl Space/Basement Excavation Crew 8 hrs Fri 2/21/03 Fri 2/21/03 100%
18 Foundation Block Work Masonry Crew 40 hrs Mon 2/24/03 Fri 2/28/03 100%
19 Well Installation Well Subcontractor 16 hrs Tue 3/25/03 Wed 3/26/03 100%
20 Get Commitments Salty Dog Properties Project Manager 8 hrs Mon 2/10/03 Mon 2/10/03 100%
21 Get Delivery date from Manufacturer Salty Dog Properties Project Manager 8 hrs Mon 2/10/03 Mon 2/10/03 100%
22 Get Commitment from erector Salty Dog Properties Project Manager 8 hrs Mon 2/10/03 Mon 2/10/03 100%
23 Get Commitment from Crane Company Salty Dog Properties Project Manager 8 hrs Mon 2/10/03 Mon 2/10/03 100%
24 Subcontractor Notification Salty Dog Properties Project Manager 8 hrs Tue 2/11/03 Tue 2/11/03 100%
25 Notify Erector Salty Dog Properties Project Manager 8 hrs Tue 2/11/03 Tue 2/11/03 100%
26 Notify Crane Company Salty Dog Properties Project Manager 8 hrs Tue 2/11/03 Tue 2/11/03 100%
27 Notify Plumbing Contractor Salty Dog Properties Project Manager 8 hrs Tue 2/11/03 Tue 2/11/03 100%
29 Notify Electrical Contractor Salty Dog Properties Project Manager 8 hrs Tue 2/11/03 Tue 2/11/03 100%
30 Weather Status Check Salty Dog Properties Project Manager 1 hr Sun 5/11/03 Sun 5/11/03 100%
31 Make Go or No Go determination Salty Dog Properties Project Manager 0.25 hrs Sun 5/11/03 Sun 5/11/03 100%
32 House Completion Salty Dog Properties Project Manager 278 hrs Mon 5/12/03 Mon 6/16/03 100%
33 Receive house Erector Crew 8 hrs Mon 5/12/03 Mon 5/12/03 100%
34 Set and weather House Erector Crew 8 hrs Tue 5/13/03 Tue 5/13/03 100%
35 Electrical Hookups and Finished Electrical Crew 16 hrs Wed 5/14/03 Thu 5/15/03 100%
36 HVAC installation HVAC Crew 24 hrs Wed 5/14/03 Fri 5/16/03 100%
37 Siding Installation Carpentry Crew 40 hrs Mon 5/19/03 Fri 5/23/03 100%
38 Interior Finish Carpentry Crew 72 hrs Sat 5/24/03 Sun 6/1/03 100%
39 Flooring Installation Flooring Subcontractor 24 hrs Mon 6/2/03 Wed 6/4/03 100%
40 Plumbing Hookups (exterior) Plumbing Crew 32 hrs Wed 5/14/03 Sat 5/17/03 100%
41 Plumbing fixture installation Plumbing Crew 16 hrs Mon 5/19/03 Tue 5/20/03 100%
42 Electrical inspection Local Building Authority 2 hrs Tue 6/10/03 Tue 6/10/03 100%
43 Plumbing inspection Local Building Authority 2 hrs Tue 6/10/03 Tue 6/10/03 100%
44 HVAC inspection Local Building Authority 2 hrs Tue 6/10/03 Tue 6/10/03 100%
45 Final Grading Excavation Crew 8 hrs Fri 6/6/03 Fri 6/6/03 100%
46 Landscaping Lanscaping contractor 24 hrs Wed 6/11/03 Sat 6/14/03 100%
47 Final Cleanup Carpentry Crew 8 hrs Sat 6/14/03 Sun 6/15/03 100%
48 Receive U and O Salty Dog Properties Project Manager 8 hrs Sun 6/15/03 Mon 6/16/03 100%

 