Project Start:
Project Finish: |
Mon 2/10/03
Mon 6/16/03
|
| ID |
Task
Name |
Duration |
Start |
Finish |
Resource
Names |
% Complete |
| 1 |
Project
Quotes |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty
Dog Properties Project Manager |
100% |
| 2 |
Get
Quotes for Well |
2 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
Salty
Dog Properties Project Manager |
100% |
| 3 |
Get
Quotes for excavation footers and drain field |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty
Dog Properties Project Manager |
100% |
| 4 |
Get
Quotes for Masonry work |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty
Dog Properties Project Manager |
100% |
| 5 |
Place
Orders |
90 days |
Wed 2/12/03 |
Mon 5/12/03 |
Salty
Dog Properties order processing |
100% |
| 6 |
Place
work order with excavator |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
Salty
Dog Properties order processing |
100% |
| 7 |
Place
order with Block/Brick supplier |
2 hrs |
Wed 2/12/03 |
Wed 2/12/03 |
|
100% |
| 8 |
Place
work order with Mason |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
Salty
Dog Properties order processing |
100% |
| 9 |
Order
Well |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
Salty
Dog Properties order processing |
100% |
| 10 |
Order
Gravel, etc for driveway |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
|
100% |
| 11 |
Order
House from manufacturer |
90 days |
Wed 2/12/03 |
Mon 5/12/03 |
Salty
Dog Properties order processing |
100% |
| 12 |
Lot
Preparation |
45 days |
Mon 2/10/03 |
Wed 3/26/03 |
Excavation
Crew |
100% |
| 13 |
Lot
Clearing |
5 days |
Mon 2/10/03 |
Fri 2/14/03 |
Excavation
Crew |
100% |
| 14 |
Construction
Drive Installation |
2 days |
Mon 2/10/03 |
Tue 2/11/03 |
Excavation
Crew |
100% |
| 15 |
Excavate
for Footers |
1 day |
Tue 2/18/03 |
Tue 2/18/03 |
Excavation
Crew |
100% |
| 16 |
Pour
Footers |
1 day |
Wed 2/19/03 |
Wed 2/19/03 |
Excavation
Crew |
100% |
| 17 |
Prepare
Crawl Space/Basement |
1 day |
Fri 2/21/03 |
Fri 2/21/03 |
Excavation
Crew |
100% |
| 18 |
Foundation
Block Work |
5 days |
Mon 2/24/03 |
Fri 2/28/03 |
Masonry
Crew |
100% |
| 19 |
Well
Installation |
2 days |
Tue 3/25/03 |
Wed 3/26/03 |
Well
Subcontractor |
100% |
| 20 |
Get
Commitments |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty
Dog Properties Project Manager |
100% |
| 21 |
Get
Delivery date from Manufacturer |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty
Dog Properties Project Manager |
100% |
| 22 |
Get
Commitment from erector |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty
Dog Properties Project Manager |
100% |
| 23 |
Get
Commitment from Crane Company |
1 day |
Mon 2/10/03 |
Mon 2/10/03 |
Salty
Dog Properties Project Manager |
100% |
| 24 |
Subcontractor
Notification |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty
Dog Properties Project Manager |
100% |
| 25 |
Notify
Erector |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty
Dog Properties Project Manager |
100% |
| 26 |
Notify
Crane Company |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty
Dog Properties Project Manager |
100% |
| 27 |
Notify
Plumbing Contractor |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty
Dog Properties Project Manager |
100% |
| 28 |
Notify
HVAC Contractor |
1 hr |
Tue 2/11/03 |
Tue 2/11/03 |
|
100% |
| 29 |
Notify
Electrical Contractor |
1 day |
Tue 2/11/03 |
Tue 2/11/03 |
Salty
Dog Properties Project Manager |
100% |
| 30 |
Weather
Status Check |
1 hr |
Sun 5/11/03 |
Sun 5/11/03 |
Salty
Dog Properties Project Manager |
100% |
| 31 |
Make
Go or No Go determination |
0.25 hrs |
Sun 5/11/03 |
Sun 5/11/03 |
Salty
Dog Properties Project Manager |
100% |
| 32 |
House
Completion |
35.75 days |
Mon 5/12/03 |
Mon 6/16/03 |
Salty
Dog Properties Project Manager |
100% |
| 33 |
Receive
house |
8 hrs |
Mon 5/12/03 |
Mon 5/12/03 |
Erector
Crew |
100% |
| 34 |
Set
and weather House |
1 day |
Tue 5/13/03 |
Tue 5/13/03 |
Erector
Crew |
100% |
| 35 |
Electrical
Hookups and Finished |
2 days |
Wed 5/14/03 |
Thu 5/15/03 |
Electrical
Crew |
100% |
| 36 |
HVAC
installation |
3 days |
Wed 5/14/03 |
Fri 5/16/03 |
HVAC
Crew |
100% |
| 37 |
Siding
Installation |
5 days |
Mon 5/19/03 |
Fri 5/23/03 |
Carpentry
Crew |
100% |
| 38 |
Interior
Finish |
9 days |
Sat 5/24/03 |
Sun 6/1/03 |
Carpentry
Crew |
100% |
| 39 |
Flooring
Installation |
3 days |
Mon 6/2/03 |
Wed 6/4/03 |
Flooring
Subcontractor |
100% |
| 40 |
Plumbing
Hookups (exterior) |
4 days |
Wed 5/14/03 |
Sat 5/17/03 |
Plumbing
Crew |
100% |
| 41 |
Plumbing
fixture installation |
2 days |
Mon 5/19/03 |
Tue 5/20/03 |
Plumbing
Crew |
100% |
| 42 |
Electrical
inspection |
2 hrs |
Tue 6/10/03 |
Tue 6/10/03 |
Local
Building Authority |
100% |
| 43 |
Plumbing
inspection |
2 hrs |
Tue 6/10/03 |
Tue 6/10/03 |
Local
Building Authority |
100% |
| 44 |
HVAC
inspection |
2 hrs |
Tue 6/10/03 |
Tue 6/10/03 |
Local
Building Authority |
100% |
| 45 |
Final
Grading |
1 day |
Fri 6/6/03 |
Fri 6/6/03 |
Excavation
Crew |
100% |
| 46 |
Landscaping |
3 days |
Wed 6/11/03 |
Sat 6/14/03 |
Lanscaping
contractor |
100% |
| 47 |
Final
Cleanup |
1 day |
Sat 6/14/03 |
Sun 6/15/03 |
Carpentry
Crew |
100% |
| 48 |
Receive
U and O |
1 day |
Sun 6/15/03 |
Mon 6/16/03 |
Salty
Dog Properties Project Manager |
100% |
| Task ID |
Task
Name |
Resource
Name |
Work |
Start |
Finish |
% Work Complete |
| 1 |
Project
Quotes |
Salty
Dog Properties Project Manager |
8 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
100% |
| 2 |
Get
Quotes for Well |
Salty
Dog Properties Project Manager |
2 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
100% |
| 3 |
Get
Quotes for excavation footers and drain field |
Salty
Dog Properties Project Manager |
8 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
100% |
| 4 |
Get
Quotes for Masonry work |
Salty
Dog Properties Project Manager |
8 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
100% |
| 5 |
Place
Orders |
Salty
Dog Properties order processing |
720 hrs |
Wed 2/12/03 |
Mon 5/12/03 |
100% |
| 6 |
Place
work order with excavator |
Salty
Dog Properties order processing |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
100% |
| 8 |
Place
work order with Mason |
Salty
Dog Properties order processing |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
100% |
| 9 |
Order
Well |
Salty
Dog Properties order processing |
1 hr |
Wed 2/12/03 |
Wed 2/12/03 |
100% |
| 11 |
Order
House from manufacturer |
Salty
Dog Properties order processing |
720 hrs |
Wed 2/12/03 |
Mon 5/12/03 |
100% |
| 12 |
Lot
Preparation |
Excavation
Crew |
240 hrs |
Tue 2/25/03 |
Wed 3/26/03 |
100% |
| 13 |
Lot
Clearing |
Excavation
Crew |
40 hrs |
Mon 2/10/03 |
Fri 2/14/03 |
100% |
| 14 |
Construction
Drive Installation |
Excavation
Crew |
16 hrs |
Mon 2/10/03 |
Tue 2/11/03 |
100% |
| 15 |
Excavate
for Footers |
Excavation
Crew |
8 hrs |
Tue 2/18/03 |
Tue 2/18/03 |
100% |
| 16 |
Poor
Footers |
Excavation
Crew |
8 hrs |
Wed 2/19/03 |
Wed 2/19/03 |
100% |
| 17 |
Prepare
Crawl Space/Basement |
Excavation
Crew |
8 hrs |
Fri 2/21/03 |
Fri 2/21/03 |
100% |
| 18 |
Foundation
Block Work |
Masonry
Crew |
40 hrs |
Mon 2/24/03 |
Fri 2/28/03 |
100% |
| 19 |
Well
Installation |
Well
Subcontractor |
16 hrs |
Tue 3/25/03 |
Wed 3/26/03 |
100% |
| 20 |
Get
Commitments |
Salty
Dog Properties Project Manager |
8 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
100% |
| 21 |
Get
Delivery date from Manufacturer |
Salty
Dog Properties Project Manager |
8 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
100% |
| 22 |
Get
Commitment from erector |
Salty
Dog Properties Project Manager |
8 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
100% |
| 23 |
Get
Commitment from Crane Company |
Salty
Dog Properties Project Manager |
8 hrs |
Mon 2/10/03 |
Mon 2/10/03 |
100% |
| 24 |
Subcontractor
Notification |
Salty
Dog Properties Project Manager |
8 hrs |
Tue 2/11/03 |
Tue 2/11/03 |
100% |
| 25 |
Notify
Erector |
Salty
Dog Properties Project Manager |
8 hrs |
Tue 2/11/03 |
Tue 2/11/03 |
100% |
| 26 |
Notify
Crane Company |
Salty
Dog Properties Project Manager |
8 hrs |
Tue 2/11/03 |
Tue 2/11/03 |
100% |
| 27 |
Notify
Plumbing Contractor |
Salty
Dog Properties Project Manager |
8 hrs |
Tue 2/11/03 |
Tue 2/11/03 |
100% |
| 29 |
Notify
Electrical Contractor |
Salty
Dog Properties Project Manager |
8 hrs |
Tue 2/11/03 |
Tue 2/11/03 |
100% |
| 30 |
Weather
Status Check |
Salty
Dog Properties Project Manager |
1 hr |
Sun 5/11/03 |
Sun 5/11/03 |
100% |
| 31 |
Make
Go or No Go determination |
Salty
Dog Properties Project Manager |
0.25 hrs |
Sun 5/11/03 |
Sun 5/11/03 |
100% |
| 32 |
House
Completion |
Salty
Dog Properties Project Manager |
278 hrs |
Mon 5/12/03 |
Mon 6/16/03 |
100% |
| 33 |
Receive
house |
Erector
Crew |
8 hrs |
Mon 5/12/03 |
Mon 5/12/03 |
100% |
| 34 |
Set
and weather House |
Erector
Crew |
8 hrs |
Tue 5/13/03 |
Tue 5/13/03 |
100% |
| 35 |
Electrical
Hookups and Finished |
Electrical
Crew |
16 hrs |
Wed 5/14/03 |
Thu 5/15/03 |
100% |
| 36 |
HVAC
installation |
HVAC
Crew |
24 hrs |
Wed 5/14/03 |
Fri 5/16/03 |
100% |
| 37 |
Siding
Installation |
Carpentry
Crew |
40 hrs |
Mon 5/19/03 |
Fri 5/23/03 |
100% |
| 38 |
Interior
Finish |
Carpentry
Crew |
72 hrs |
Sat 5/24/03 |
Sun 6/1/03 |
100% |
| 39 |
Flooring
Installation |
Flooring
Subcontractor |
24 hrs |
Mon 6/2/03 |
Wed 6/4/03 |
100% |
| 40 |
Plumbing
Hookups (exterior) |
Plumbing
Crew |
32 hrs |
Wed 5/14/03 |
Sat 5/17/03 |
100% |
| 41 |
Plumbing
fixture installation |
Plumbing
Crew |
16 hrs |
Mon 5/19/03 |
Tue 5/20/03 |
100% |
| 42 |
Electrical
inspection |
Local
Building Authority |
2 hrs |
Tue 6/10/03 |
Tue 6/10/03 |
100% |
| 43 |
Plumbing
inspection |
Local
Building Authority |
2 hrs |
Tue 6/10/03 |
Tue 6/10/03 |
100% |
| 44 |
HVAC
inspection |
Local
Building Authority |
2 hrs |
Tue 6/10/03 |
Tue 6/10/03 |
100% |
| 45 |
Final
Grading |
Excavation
Crew |
8 hrs |
Fri 6/6/03 |
Fri 6/6/03 |
100% |
| 46 |
Landscaping |
Lanscaping
contractor |
24 hrs |
Wed 6/11/03 |
Sat 6/14/03 |
100% |
| 47 |
Final
Cleanup |
Carpentry
Crew |
8 hrs |
Sat 6/14/03 |
Sun 6/15/03 |
100% |
| 48 |
Receive
U and O |
Salty
Dog Properties Project Manager |
8 hrs |
Sun 6/15/03 |
Mon 6/16/03 |
100% |